View the development and track the progress of your home at 63° East.
1st-lift-column-concrete-in-progress-in-C1
PCC-in-progress-in-C2
Excavation-in-progress-in-C-3
Shuttering-for-footing-in-C3
Retaining-wall-shuttering-in-progress-south-side
Tower-C-work-in-progress
Tower-C-nw-corner-retaining-wall-concrete-complete
1st-lift-of-columns-in-progress-in-tower-C
SW-corner-retaining-wall-concrete-complete-and-balance-areas-in-progress
Retaining-wall-bar-bending-in-progress-on-the-east-side-of-tower-C
1st-slab-shuttering-in-progress-in-tower-C
Bar-bending-in-progress-for-1st-structural-slab-in-tower-C
tower crane erection complete for ancillary works
pour-3 area c1-block shuttering in progress
pour-1 area C1-block bar bending in progress
pour-1 area c1-block side shuttering complete
C2-block 2nd-lift-column shuttering in progress
Pour 3 Area C1 block-side-shuttering-complete
Pour 1 Area C1 block-Concrete-Complete
Pour 1 Area C1 block-1st-lift-columns-complete
Pour 2 Area C1 block-bar-bending-in-progress-for-slab
Pour 3 Area C1 block-bar-bending-and-electrical-works-in-progress
1st-lift column complete for 2nd-structural slab in C1
2nd-structural slab in progress in C2
Shuttering in progress for 2nd-structural slab
C3-from-north-side
1st-structural slab work in progress in C3
Slab shuttering and bar bending in progress for c1
podium slab completed for c1
shuttering in progress for c2
slab shuttering work in progress for c3
bar bending in progress for c3
North East corner C3 Reinforcement & Shuttering Work Progress
North West corner C1 1st floor Reinforcement & Shuttering Work Progress
Slide-3
Slide-4
Slide-5
Slide-6
C1 - 3rd floor shuttering under progress
C2 - 2nd floor slab reinforcement work under progress
C3- 1st floor slab and wall shuttering under progress
Veiw form South East corner
Veiw form South West Corner
Veiw From North West Corner
Veiw from North Side
C1-10th Floor Work completion, C2-10th Floor Work Under Progress, C3-09th Floor Work Under progress
D1-Foundation completed & Sump work under progress
D2 & D3 Foundation Completed progress concrete under process
C1-13th Floor Work under progress, C2-12th Floor Work Under Progress, C3-12th Floor Work Under progress
D1-Second Lift column and STP PCC complete and refilling in progress
D2 & D3 Block Second Lift column, and UG tank Raft complete, retaining wall and reinforcement work in progress
Tower-C- Terrace Elevation work under progress
Putty work for C1-Block First Floor Started
D1-Block Lower Basement slab & STP work under progress
Tower-D-D2-Block Lower Basement slab & UG Sump work under progress
D1-Block Lower Basement slab & STP work under progress
Putty work for C1-Block First Floor Started
Tower-C- Terrace Elevation work under progress
Tower-D-D2-Block Lower Basement slab & UG Sump work under progress
Putty work in Progress-C1-Block till 10th Floor , C2 Block - Till 05th Floor and C3-Block-Till-6th Floor Completed
Terrace Elevation work in progress
Tileing Work Started For-C1 Block
Tower C Elevation
Tower-D Podium Slab Work Under Progress
Bathroom Tiling Work in progress for C-Tower
D-1 upper stilt slab work under progress
D1 & D2 podium slab work under progress
Floor Tiling work in progress for C-tower
Tower -C Elevation
1st Coat Putty work in Progress-C-1 till 12th Floor,C-2 till 09th Floor,C-3 till 08th Floor
Bathroom Wall tile work in progress
D-1 Podium Completed
D-2 & D-3 Podium Work in Progress
Kitchen Dado Tile work in Progress
South Side Balcony railing work in progress C-1 till 08th Floor, C-2 till 08th Floor, C-3 till 08th Floor